Sat Mar 19, 2022 4:50 pm
Yea and it is NOT getting better any time soon.
We are forced to purchase parts from Brokers who charge 2x to 3x the normal cost.
For example we are trying to secure 75,000 (all they have) current sensors from Broker for $3.XX each normally cost $1.20 each.
MOSFETs also can not get
SOC (Main Chip) Increased costs but some POs 12 months past due
A2D, LED Drivers, and the list goes on. If you place an order today the lead time is 52 - 72 weeks and that is optimistic and would probably be late.
Only 3 more LONG years until a competent administration (Hopefully) gets back into office.
Support is handled on the Forums not in Emails and PMs.
Before you ask a question use the Search function to see it has been answered before.
To do an Advanced Search click the magnifying glass in the Search Box.